The Haven of Athens Monthly Progress

The Haven of Athens is the newest student housing community serving college students in Athens, Georgia. The Haven of Athens will offer unique, state of the art amenities for its residents, both inside and outside of multi-bedroom, stylistic cottages. Scroll down to read and view the latest progress on the project.

July, 2020

Dear Investors:

SCG is pleased to report the progress on The Heaven of Athens site for the close of June, 2020. As of June 30th, 2020, all preleasing for August 1st is complete. Despite bad weather and COVID-19, we are looking forward to full-rental in August, 2020. In addition to a full preleasing, construction is almost complete. 

As of the end of June, 2020, we are happy to report the following project progress:
  
  • Footings are completed for 69 out of the 69 units
  • Slab work is completed for 69 out of 69
  • Framing is complete for 69 out of 69
  • MEPs is complete for all 69 units
  • Insulation, 69 out of 69
  • Drywall complete, 69 out of 69
  • Siding complete, 69 out of 69
  • Exterior Paint complete, 69 out of 69
  • Interior paint complete 99%
  • Sanitary sewer installation is 100%
  • Storm sewer installation is 100%
  • Grading – 99% complete
  • Curb installation is 100% complete
  • Pool Construction, 95% complete
  • Water Main Installation 100%
  • Water Service Installation 100%
  • Cabinet installation 100%
  • Permanent Power for all houses 100%
  • Final Electrical Inspections complete 100%
  • HVAC Trim out 90%
  • Low Voltage Trim Out 90%
  • Sidewalk installation 90%
  • Asphalt 85% complete
  • Fencing installation – 75%
  • Irrigation installation – 90%
  • Well for irrigation complete
  • Tile backsplashes 95%
  • Appliance installation – 90% complete
  • Kentucky Cir. Rd. Improvements – 50%
  • Plumbing Trim Out – 80%
  • Water Meter installation – 35%
  • Landscaping – 35%
  • All Site Lighting – 100%
  • Entrance Sign – 100%

We are thankful for the progress we have made and very happy that we are 100% preleased for August 1st. We are in a very good position, and we expect to wrap up another successful project while meeting or exceeding all of our goals.

Cost projection: We are still on budget and remaining aligned with the original forecast.

  • The budget, for conservative purposes, is kept at $19.5 million as initially budgeted, but we were able to increase contingency item from $870,760 as initially forecasted to $1,261,137
  • Regarding construction, out of the $ 16.215.184, progress has been made by $12,397,648 budget and we remain aligned with our original forecast.

Build and Budget Schedule

Each month we’ll update the construction schedule and budget, with start, committed, forecast and finished dates and numbers.